KPU-A & C Frame-5 Major Overhaul Gas Turbine

18-12-2017

Completed hot gas path inspection (24,000 hrs.) of KPU A and C gas turbines on Sep. & Oct. 2017, these jobs are consider a major overhaul maintenance were carryout by Yemeni technicians and supervised by Yemeni engineer.

During these jobs all major parts of gas turbine were changed.
These major overhauls improve the performance of gas turbine and increase the production of compressed gas.

 