Replace GTG-B Power Turbine At CPU
15-01-2018Completed the replacement of Generator’s B turbine was working more than 177,000 hrs at the central production unit under the supervision and implementation of Yemeni engineers and technicians.
The work took about 29 days and is considered one of the main maintenance works.
The work started on Dec. 01, 2017 and finish on Dec. 28, 2017. All mechanical and operational parameter are within acceptable limits.